Sharon Standing Building Committee

June 8, 2004

Minutes

 

 

Members Present:  Dave Belton, Deborah Benjamin, Donald Gilligan, Gordon Gladstone, Joel Wolk

 

Members Absent: Fred Clay, Bill Croteau

 

Guests Present:  Ken Wertz, Peter Collins, Roger Hoit, Ellen Gleason, Sue Lechter, Tony Pruner, Judy Freedberg, Ron Laprise, Scott Pray

 

The meeting opened at 6:30pm at the Sharon Town Offices

 

Administrative Matters

Minutes:

MOTION:       To vote to accept the minutes of May 25, 2005 as corrected

(Belton/Gilligan – Unanimous)

 

Invoices:         East Elementary School

1.      Heery International – Inv. # 42544 – monthly Fee - $17,000 (Gladstone/Belton – unanimous)

2.      Merrimack Education Center (PO # FFEtech-east-1 – partial) $4848.38 (Belton/Gladstone – unanimous)

3.      MCI (office phone – monthly) $28.42 (Belton/Gladstone – unanimous)

4.      DF Pray Requisition # 22 - $213,213.00 (Belton/Gladstone – unanimous)

 

Correspondence: 

Middle School: 

·        Bid tabulation – asbestos project (in member’s packets)

·        Bid rejection letter (in members’ packets)

 

Cottage Street School Project:

·        A copy of meeting minutes sent to DF Pray per their request.

·        A copy of a rejection of Site As Built drawings

·        A copy of a memo sent to P. Costello from SSBC RE: K & K request to withdraw demand

·        A copy of a memo from DPW to SPS RE: site punch list (in member’s packet)

·        A letter to Atty. James from Atty. Costello RE: public records request

East Elementary School Project:

·        A memo to P. Costello from SSBC RE: Capeway Roofing Demand (in member’s packet)

·        A letter to DF Pray from Heery RE: Roof leaks – building D (in member’s packet)

·        A copy of a letter from DPW to SPS RE: site punch list (in member’s packet)

·        A copy of a memo to SPS from SSBC RE: East FF & E budget information

·        A copy of DF Pray Claim # 60 – CCD request

·        A copy of DF Pray Claim # 123 VWC

·        A copy of DF Pray Claim # 123 VWC – CCD request

·        A copy of DF Pray Claim # 127 – EDPM

·        A copy of DF Pray Claim # 126 – Brick

·        A copy of DF Pray Claim #125 – SF-2

·        A copy of DF Pray Claim # 124 – Specify Walls

·        UTS Testing Report – 5/10/04

·        Heery Daily Reports – 5/17/04 – 5/21/04

·        SHR Logs

 

 

Community Center Repairs: There have been some problems at the community center due to the failure of the ceiling in the front foyer and dining room areas.  Proposals from structural engineers/architectural firms will be solicited to determine the impact of this situation on code compliance and structural integrity of the building.

 

East Elementary School Project

Construction status report (Heery and SHR) - Mr. Peter Collins gave an overview of the construction project at the East Elementary School.  There has been an effort to clear up the backlog of outstanding paperwork that was needed to move the project forward.  There has been a renewed effort by both the contractor and sub contractors to complete the project.  Mr. Collins discussed the activity report photos that display the types of finish work that is ongoing at this time.  The increase in staffing has had a positive impact on the project.  Mr. Collins stated that he feels that the increase in staffing is a direct result of the resolution of the outstanding paperwork.  The kitchen walls will be treated with fiberglass treated panels.  The work in the cafetorium is ongoing with the installation of the sprinklers, ductwork, wall finish and floor finish.  The roofing contractor has been onsite to make the front entrance watertight.  There has been a resolution of the steel column detail that was outstanding.  This entrance should be completed by the end of July.  The fire alarm system is being installed. There will be two annunciator panels - one at each entrance.  There are four smaller roof top air conditioning units because the roof frame could not support the larger units.  The boiler units have been installed and tested.  There has been some concrete work that has taken place last week. More concrete work will take place in the next two weeks.  The site will be prepared for hydro- seeding within the next two weeks.

 

Roof Testing – The committee reviewed the report that was issued by the testing agency RJ Kenny.  The corrective work needs to be completed by the roofing contractor prior to further investigative work to determine the proper way to correct this situation.  The RJ Kenny report stated that the areas in question are in the vicinity of the dormers, which has not been properly installed in accordance with the project documents.

 

Other Issues

MOTION:       To authorize the chair or vice chair to sign Change Order # 3 in the amount of $59,097.00 (Benjamin/Gladstone – unanimous)

MOTION:       To authorize the chair or vice chair to sign Change Order  # 4 in the amount of $ 158,694.00 (Belton/Gilligan – unanimous)

 

Completion Date- The committee discussed the request from the contractor to forward an interim requisition to the cover change order work.  Members of the committee asked about the possibility of completing the job on August 1st.  Mr. Scott Pray, owner of DF Pray stated that with the renewed spirit of cooperation that he anticipates the project would be completed by the August 1st date unless that there are any unforeseen complications. 

 

Site Work - Mr. Collins informed the committee that there was some additional site work that was needed to improve the fields.  It was the consensus of the committee not to issue new scope work

 

Cottage Elementary School project - Mr. Ken Wertz gave an overview of the project and commented that the electric work is still the major item on the punch list.  The science counters have not been installed and the color was re-submitted to the architect's office.  Mr. Laprise stated that there would be a lot of work taking place this weekend.  Exterior and interior punch list and contract work items will be completed this weekend

 

Punch list and closeout status (SHR)- There was discussion regarding the installation of the fresh air intake louvers near the bus turn around.  The chairman asked Mr. Hoit to get a written response from the engineers.  The committee asked for this response and will review this item to determine if a design change may be necessary.  Mr. Wertz asked about the status of the stage light installation.  Mr. Hoit will look into this situation and respond back to the committee to get this resolved.  Questions were also raised about the accessibility of the boys gang bathroom and the clearance in the kitchen.  There are still several electrical areas that need to be resolved.  Mr. Laprise stated that there would be an electrician on site this week. The chairman asked that the architect works on this project and has a full report within the next two weeks.

 

Sharon Middle School Abatement Project

Project and bid status - The asbestos abatement will be going out to bid on June 23, 2003.  KBA was invited to July 6th meeting to give an overview of the project status.

MOTION:       To allow the chairman or vice chairman to issue a letter of award - for the abatement work - after the bids have been reviewed. (Benjamin/Gilligan)

 

Executive Session (pending legal issues)  - The members of the committee were polled to go into executive session to discuss pending litigation and legal strategy concerning the Cottage and East Elementary School construction projects.  The members of the committee asked Roger Hoit, Ken Wertz, Tony Pruner and Peter Collins to attend this meeting.  The following members voted in the affirmative to go into executive session: Dave Belton, Deborah Benjamin, Bill Croteau, Donald Gilligan, Gordon Gladstone, and Joel Wolk

 

The committee will come out of executive session to adjourn.

 

The meeting adjourned at 9.20pm. 

 

Respectfully submitted,

 

 

 

Maureen R. Doherty - Recording Secretary

 

 

 