SHARON STANDING BUILDING COMMITTEE
 MINUTES
 
APRIL 25, 2006

 

This meeting is closed to public comment unless the speaker is on the agenda.

 

Members Present:  Bill Croteau, Deb Benjamin, Gordon Gladstone, Joel Wolk, Colleen Tuck, Fred Clay, Greg Waugh, Rich Slater, Dave Belton

 

Associate Members Present:  Rob Maidman, Rick Rice, Arnold Kublin, Jay Bronstein, 

Steve Lesco,

 

Guests Present:   Kevin Turley, Tom Scarlata, Norma Fitzgerald

 

Administration
    The following Meeting minutes (
4-4-06, 4-11-06) were approved as amended. (Wolk/Belton – unanimous)

     Future meetings:  May 9 & 23, June 6 & 20

 

Middle School HVAC

The following correspondence was submitted for review.
 DCAM Evaluation-tabled from
4-4-06, 50% Interim Evaluation Report for Fraser Engineering (DCAM Request) - The individual members of the committee scored the contractor and the average score is 93.  The project manager will complete the evaluation for the chairman to sign. 

 Architects Report 4-3-06

     Invoices:

·         Merrick Louison & Costello $ 17.50 (Tuck/Belton - unanimous)

 

The chairman discussed the meeting he had with KBA principal, Michael McKeon, to reduce the rate charged by the KBA project manager.  KBA will be issuing a credit of $9,000 for the rate differential. 

 

Middle School Roof

The following correspondence was submitted for the committee review.
Warranty and certification letters from Sarnafil, Inc.

 

Cottage and East Elementary School Close-out

The following correspondence was submitted for review

Correspondences regarding public records requests    

Invoices:

·         Merrick Louison & Costello $ 1295.00 - Cottage (Belton/Clay - unanimous)

·         Merrick Louison & Costello  $ 52.50 – East (Belton/Clay - unanimous)

 

The committee discussed the preparation of the audit materials for the Cottage and East Elementary School.

 

 

Wilber School Project
     Invoices

·         STV Incorporated - $15,933.75 (Clay/Wolk - unanimous)

 

Community Center Project
     General bid review - Mr. Tom Scarlata gave an overview of the bids that were received from the General Contractors.  Mr. Scarlata had spoken to the apparent low bidder, Paul J. Rogan Company regarding the differences in the bid estimate and the cost estimate.  The abatement and demolition costs seem to be in line with the DG Jones estimate.   The electrical bids showed the largest increase in price.  There are not a lot of areas where the project can be cut.  The project is a renovation of an existing building.  The architect submitted a list of items that could be changed to reduce the price by $200,000 - Change Clay Brick Masonry on new additions to jumbo brick or colored CMU, Lower Stair/  Stop at upper level.  Provide only ladder and hatch access to roof.  Reduce extent of canopies at exterior, Simplify or delete millwork in Ballroom, Where size allows, change wood clad windows to vinyl, Change doors at COA level to hollow metal, delete lites and grilles.  There was discussion regarding how unknown conditions and the impact on the project.  It was determined that this was not an impact.  Member Maidman stated that he feels that the uncertainty of the market has affected the price of the bids.  Member Waugh stated that the Central Register has been about three times thicker than it normally is.  Member Clay stated that the project is 20% over on the subs and 20% over on the general contractor. 

Three options are available.

Do not do the project

Re-bid the project and do not pre-qualify the subs and re-bid the project

Go with the project as it was bid. 

 

It is the unanimous consensus of the SSBC including associate members to go forward at town meeting for the difference of $1,384,000.00

 

The following correspondence was submitted for the committee review.

  1. A letter from the BOH to Site Engineering Consultants, Inc. RE: Community  Center – Approval of Septic Design
  2. Copy of Town Meeting vote – 11-14-05 – Community Center
         Invoices (Wolk/Belton – unanimous)

·         Trailer, Storage, Newspaper Ads (Community News, McNamara, Miniwarehousing, Williams Scotsman & Handihouse) $ 4273.58

·         Merrick Louison & Costello $ 157.50

 

Respectfully submitted:

Maureen R. Doherty

Maureen R. Doherty – Project Manager

 

 

Gordon Gladstone                   October 3, 2006

Signature of Chair                                                       Date of Acceptance

 

 

 

The