Sharon Standing Building Committee
Meeting Minutes
March 31, 2010
Members Present: Chair Gordon Gladstone, Fred Clay, Bill Croteau, Rick Rice, Steve Smith, Joel Wolk, Roger Thibault and Glenn Allen
Members not Present: Colleen Tuck, Rich Slater, Vice-Chair Deb Benjamin
Others Present: Mike McKeon and David Morais - KBA Architects
Richard Marks, Joseph Sullivan, Robert White - Daedalus Projects Inc.
Michael Dupuis and Todd McCabe - Consigli Construction Co.
The meeting of the Sharon Standing Building Committee was called to order at 6:39 p.m. in the Conference Room at the Community Center.
1. Administration
Approval of Minutes
MOTION: To approve the meeting Sharon Standing Building Committee minutes March 16, 2010 (Wolk/Rice) unanimous - Thibault abstained
Future Meetings: Tuesday April 13 and 27, 2010
2. Sharon Middle School Project Updates
Bob White gave the following update:
§ Re the PFA status, MSBA has all certified documents in hand;
§ Richard Marks will go over Consigli contract and send version to Town Counsel Attorney Cindy Amara and Attorney Pat Costello;
§ The Trade subcontractor prequalification meeting scheduled for Friday, April 9, 2010 at the Hearing Room at the Town Offices, 90 South Main, Street, Sharon, MA;
§ MSBA update meeting with Paul Fowkes scheduled for April 6 or 7, 2010;
§ Cost estimates based upon 60% CDs to be completed week of April 8, 2010;
§ Daedalus to be meeting with Superintendent Dr. Dunham and Consigli re CORI update;
§ Structural peer review proposals:
MOTION: To authorize to have Daedalus Projects Incorporated to engage Veitas and Veitas Engineers for the Structural Peer Review for the Sharon Middle School Project in the amount of $2,800. (Rice/Wolk) – unanimous;
§ Printing proposals:
MOTION: To authorize to have Daedalus Projects Incorporated to engage Andrew T. Johnson Co., Inc., for printing services for the Sharon Middle School Project in the amount of $15,156.25. (Rice/Wolk) – unanimous;
§ Move management RFP being prepared by DPI;
§ Commissioning Agent to be awarded by MSBA next week;
David Morais of KBA Architects gave the following Architect’s Report:
§ KBA met with the Art and Science department heads on March 9, 2010 in order to go over the final plans;
§ March 16, 2010 KBA met with the Nurse, Guidance, Special Education and Computer department heads;
§ On March 17, 2010 KBA met with Cavanaugh Tocci to go over the acoustical scope of work for the project in order to meet the MACHPS IEQC 3.2’s criteria;
§ On March 19, 2010 a partnering meeting with held between the Design team, OPM, CMr and Members of the district at the library of the Sharon Middle School – Chair Gladstone and SSBC member Colleen Tuck attended;
§ A neighborhood informational meeting was held on March 25, 2010 at the Sharon Middle School;
§ March 29, 2010 KBA, GGD, DPI and Peter O’Cain walked the route for the Force Main;
§ KBA met with Consigli, DPI, Kevin O’Rourke and Ken Wertz to review/discuss Consigli’s latest phasing plans;
§ Early Release (Phase I) packages for Site, Steel, Concrete and Force Main will be released to the CM at Risk on April 5, 2010;
§ ZBA hearing scheduled for April 14, 2010;
§ The MSBA 90% Construction Document submission is scheduled for April 15, 2010. Documents to be distributed to Town building officials for their review and approval;
§ The Construction Documents (Phase II) scheduled to go out to bid the first week of May 2010.
Invoices
MOTION: approve the invoice from Daedalus Projects Incorporated dated February 28, 2010, Invoice #100218 for $12,000.00 (Wolk/Clay) – unanimous
MOTION: approve the invoice from Kaestle Boos Associates, Inc., dated February 27, 2010, Invoice #10 for $206,802.52 (Wolk/Clay) – unanimous
Insurance
MOTION: To authorize the SSBC Chair or Vice Chair to authorize Weiner Company to proceed for the construction and renovation at the Middle School with Travelers for the premium of $125,435 ($25,000 deductible - $3,000,000 additional ordinance and law coverage for an increased premium of $1,500) effective date May 1, 2010. (Wolk/Croteau) - unanimous
Member Joel Wolk recused himself from the meeting at 8:30 p.m.
Todd McCabe of Consigli Construction Co. gave the following weekly preconstruction status report :
§ Subcontractor reference checking results have been sent to DPI;
§ Subcontractor Prequalification package review started;
§ Review and presentation of Early Release Pump Package;
§ 60% MEP review – presentation of findings to team;
§ CORI meeting held with team;
§ Finalizing phasing plans;
§ 60% drawing set out to early release non trade subs for review;
§ Request for Information (RFIs) sent to KBA for review;
§ MSBA Preview meeting to be held on April 6, 2010;
§ Review of MEP systems with Ed Dubois and Ken Wertz on April 7, 2010;
§ Early release drawings due April 5, 2010;
§ Early release development continuing – target delivery date April 14, 2010;
§ Investigation of existing building – will coordinate with Ken Wertz.
MOTION: To adjourn the meeting at 9:10 p.m. (Rice/Smith) unanimous
Submitted:
Linda Morse – Recording Secretary
__________________________________ ___________________
Signature of Chair Date of Acceptance