Sharon Standing Building Committee

      Meeting Minutes

                                                   September 28, 2010

 

Members Present:     Vice-Chair Deb Benjamin, Joel Wolk, Steve Smith, Fred Clay, Bill Croteau and Glenn Allen

 

Members not Present:  Chair Gordon Gladstone, Rich Slater, Colleen Tuck, Rick Rice, Roger

                                        Thibault

 

Others Present:          Mike McKeon and David Morais - KBA Architects

                                    Joe Sullivan - Daedalus Projects Inc.

Mike Dupuis and Todd McCabe - Consigli Construction Co.

Ken Wertz, Director of School Dept. of Maintenance and Operations

 

The meeting of the Sharon Standing Building Committee was called to order at 6:35 p.m. by Vice Chair Deb Benjamin in the Conference Room at the Community Center. 

 

1.         Administration

 

Approval of Minutes

 

MOTION:  To approve the Sharon Standing Building Committee Meeting Regular Session minutes of September 14, 2010 (Wolk/Allen) – unanimous – Clay, Croteau and Smith abstained

 

Future Meetings: Tuesdays October 12 and 26, 2010 at the Community Center Conference Room.

 

Invoices:

 

MOTION: approve the invoice from Gelerman #16821 dated 8.21.2010 for $90.92 - (Wolk/Smith) – unanimous

 

2.         Sharon Middle School Project Updates

 

Michael Dupuis of Consigli Construction Co.

 

Todd McCabe brought to the SSBC the phased construction plan/drawing to be viewed by the Committee at their meetings.

 

 

 

 

Mike Dupuis gave the following update (documents attached dated September 28, 2010) of the Construction Manager’s Report:

 

·        Procurement

All initial critical trades have been bought – 39 trades have been bought out - discussed was also spray foam insulation, landscaping, exterior improvements scoreboards and playground equipment;

·        Status of Buyout

·        GMP Summary

·        Requisitions

·        Change Orders -  On the Change Order Committee are Fred Clay, Rick Rice and Joel Wolk – Any Change Order Committee meetings are to be posted;

·        Schedule (4 week Look Ahead attached)

·        Miscellaneous:  CORI checks/badges; Meeting on Off-Site Paving with Town Engineer Peter O’Cain; Electrical Issues Meeting held on September 15, 2010.  All open issues and changes were reviewed with the entire Team and Griffin Electric; and Signage VE meeting held on September 22, 2010.  Samples of alternates were presented to the SSBC.

·        Project Meetings continue to be held each Wednesday at 10:00 a.m. at the site construction trailer.

 

David Morais of Kaestle Boos Associates

 

David Morais updated the SSBC with the following Project Update (September 28, 2010 Architect’s Report attached):

 

Discussed was the following:  Insulated-Core Metal Wall Panels – a substitution to use Reynobond by Alcoa verses the insulated type panels that were specified was submitted. KBA finds this product to be an equal to those specified once Consigli incorporates the required insulation into the proposed system which they have acknowledged would be done.  KBA recommends support of this substitution.  There will be no change in cost.

 

The Standing Building Committee accepted KBA’s recommendation of the substitution to use Reynobond by Alcoa.

 

Signage – A substitution was requested at the signage package meeting to use plastic letters in lieu of the cast aluminum in specific locations.  The plastic letting would be used above 7’0” and that metal vertical lettering be used under 7’0”.

 

MOTION:   That the Sharon Standing Building Committee accept the Architect’s (KBA) recommendation to change the type of signage in specified areas for a potential cost savings - (Wolk/Smith) – unanimous

 

On Wednesday, October 6, 2010 there will be a walk-thru of the Middle School site at

l:00 p.m. with MSBA.

 

            Joe Sullivan - Daedalus Projects Inc.

 

Joe Sullivan gave the following update (document attached dated September 28, 2010):

 

Joe reported that Consigli is making great progress with the steel erection.  The erection crew (Champion) is scheduled to be completed with the structural steel installation by Monday, October 4, 2010.  Work in the auditorium remains slow until the coordination is complete.  All other trades are performing work in the un-occupied areas to continue forward progress for the completion of the next phase.

 

  1. New/Other Business

 

A portion of the Community Center roof is in need of repair.  The low-bid for the Sharon Community Center Roof Project was from Boston Exterior, 11 Brunswick Road, Arlington, MA in the amount of $15,890.  (document attached)

 

MOTION To authorize the Chair or Vice Chair to enter into contract with Boston Exterior

for repair of part of the Community Center roof and that DPW and SSBC will sign the

contract.  DPW will supervise.  Wolk/Smith  – unanimous – Allen abstained

 

The meeting adjourned at 8:05 p.m.

 

Submitted:

 

 

Linda Morse – Recording Secretary

 

 

__________________________________                            ___________________

Signature of Chair                                                                   Date of Acceptance

 

NOTE: All Standing Building Committee minutes and attachments will be available for the public to read at the Standing Building Committee office located at the Community Center upon request.