Sharon Standing Building Committee

          Meeting Minutes

            March 15, 2011

 

Members Present:     Chair Gordon Gladstone, Vice-Chair Deb Benjamin, Joel Wolk , Colleen Tuck, Steve Smith, Bill Croteau, Rick Rice, Fred Clay, Rich Slater, Roger Thibault and Glenn Allen

 

Others Present:   Joe Sullivan and Bob White - Daedalus Projects Inc.

                              Mike McKeon and David Morais - KBA Architects

                              Michael Dupuis and Todd McCabe - Consigli Construction Co.

                              Ahmed Idris – Baker-Wohl Architects

      Dr. Dunham, Principal O’Rourke

      Ken Wertz - School

 

The meeting of the Sharon Standing Building Committee was called to order at 6:43 p.m. at the DPI Construction Trailer, 75 Mountain Street.

 

1.         Administration

Approval of Minutes

 

MOTION:  To approve the meeting Sharon Standing Building Committee minutes of March 1, 2011 (Tuck/Rice) unanimous – Thibault abstained as he was not present at the meeting

 

Future Meetings: Tuesdays, March 22, 29 and April 12 and 26, 2011

 

Invoices:

MOTION: to approve the following invoices:

Consigli #9 for $1,228,508.59

Daedalus #110218 for $32,000

Kaestle Boos Associates #22 for $28,158.83

Eagle Leasing #’s R1308321 for $100 and R1315157 for $100

Envirotest Laboratory #47688 for $500

The above invoices were approved (Rice/Tuck) – unanimous

 

2.        Sharon Middle School Project

 

The following reports were received and are attached as part of these minutes:

KBA – Mike McKeon

Discussed was the following:

 

Carpet or lack of in the pit of the auditorium.  The SSBC took a look at the area in question re carpet or lack of in the pit of the auditorium.

 

MOTION:  To authorize the Owner’s Project Manager to have the Construction Manager (CM) to go forward with carpeting of orchestra pit at the auditorium. (Wolk/Slater) – unanimous

 

Preferred finish for the columns in the auditorium lobby was discussed.  The SSBC and the School Department reviewed KBA’s Auditorium entry design options, including relative costs and maintenance considerations, and that the SSBC would accept the School Department’s option selection (which was Option 5, having wood trim).

 

Consigli – Mike Dupuis (report attached)

Discussed was the following:

·        School administration needs to let Consigli know what to do with modulars;

·        Owner approval letter;

·        Bleachers in gym.

 

Daedalus: - Bob White (report attached)

Discussed was the following:

·        Cost Report (attached)

·        The contract for Project Management Services (Amendment 3) in the amount of $112,300 was reviewed by committee;

MOTION:  To approve the Contract for Project Management Services – Amendment No. 3 (Daedalus Projects, Incorporated) in the amount of $112,300 as aggregate for entire project for DPI.  (Wolk/Tuck) – unanimous

 

3.         High School Roof

 

Bob White (DPI) OPM for the High School Green Roof Repair Project reported to the SSBC the following:

·        Progress Report (attached)

·        DPI has submitted an OPM contract and feel proposal in the amount of $80,000 for the H.S. roof project for approval at SSBC March 15, 2011 meeting;

·        A list of designer activities have been sent to MSBA;

·        The Designer (Baker/Wohl) has participated in the pre-design meeting and has conducted extensive roof inspections, interior water damage assessment inspections, test cuts, MAZMAT testing and research of existing plans/spec for the building;

·        Attachment “B” of the Contract was discussed; (attached)

·        Project Schedule:  The GC Bids are due on April 25, 2011.

 

The following motions were made:

 

MOTION:  To authorize the Chair or Vice-Chair to enter into contract with Baker/Wohl Architects not to exceed $120,000 and for Daedalus Projects not to exceed $30,000 for services by both through contract bidding and award.  (Allen/Wolk) - unanimous

 

MOTION:  To authorize the Chair or Vice-Chair to enter into an amendment with Bohl/Wohl Architects in the amount of $80,000 and Daedalus Projects for $50,000 for additional services by both of contract administration and closeout pending approval and funding by the Town of Sharon.  (Allen/Wolk) - unanimous

 

 

MOTION:  To authorize the Chair or Vice-Chair to issue a notice to proceed to Bohl/Wohl Architects and Daedalus Projects to go forward based on prior Contract authorization for services by both through contract bidding and award.  (Allen/Wolk) - unanimous

 

Ahmed Idris – Baker-Wohl Architects – introduced himself to the SSBC and talked about the company’s experience, staffing and time commitment to the High School roof project.  Other staff members are C. Daniel Bass, Jeremy Tobin, Taulant Miloshi and Neha Arora.

 

Next Meeting:  March 22, 2011 – Community Center Conference Room at 6:30 p.m.

 

MOTION:  To adjourn the meeting at 8:15 p.m.  (Wolk/Slater) - unanimous

 

Submitted:

 

Linda V. Morse, Secretary

Sharon Standing Building Committee

 

 

__________________________________                            ___________________

Signature of Chair                                                                     Date of Acceptance