Sharon Standing Building Committee

          Meeting Minutes

          February 8, 2011

 

Members Present:     Chair Gordon Gladstone, Vice-Chair Deb Benjamin, Colleen Tuck, Steve Smith, Roger Thibault, Rick Rice, Fred Clay, Bill Croteau, Rich Slater and Glenn Allen

 

Members Not Present:  Joel Wolk   

 

Others Present:          Mike McKeon, David Morais - KBA Architects

                                    Bob White - Daedalus Projects Inc.

            Michael Dupuis - Consigli Construction Co.

            Ken Wertz, Barbara Dunham and Tim Farmer

 

The meeting of the Sharon Standing Building Committee was called to order at 6:46 p.m. at the Community Center Conference Room.

 

1.         Administration

Approval of Minutes

 

MOTION:  To approve the meeting Sharon Standing Building Committee minutes of January 18, 2011 (Smith/Benjamin) unanimous.  Clay, Croteau, and Slater abstained as they were not at the meeting.

 

Future Meetings: Tuesdays, February 15 March 1 – 15 and 29, 2011

 

Invoices:

·        Consigli #7 $1,920,307.06

·        Daedalus #110130 $72.00

·        Daedalus #110136 $171

·        Daedalus #110139 $40

·        Daedalus #101130 $510

·        Daedalus #110140 $700

·        Kaestle Boos #22 $28,120

·        Kaestle Boos #1 (KBA080818.05) $4,950

·        IKON $5016226031 $15.76

The above invoices were approved (Clay/Smith) – unanimous

 

2.        Auditorium Main Entrance Modification

 

Superintendent Dunham and future Superintendent, Tim Farmer was present to listen to the auditorium entrance doors modification discussion presented by Mike McKeon of KBA.

 

           Mike McKeon presented to the Committee the various sketches (Options A, B, C and D)                   

           which are attached as part of these minutes.

 

Option A  would require the installation of a 4’-0” door leaf and 2’-0” door leaf in lieu of the two 3’-0” doors leaves per door.  Each four-foot door would provide a total egress capacity of 284 occupants per door opening.  Consigli has estimated this change to cost approximately $6,468.00.

 

Option B allows for the doors as they are installed to remain and 6’-4” openings would be cut through the existing corridor auditorium wing walls.  This would allow for total egress capacity of 407 occupants per door opening.  Consigli has estimated this change to cost approximately $22,038.00.

 

Option C this solution is a variation of option A with an attempt to save costs.  One of the three-foot leaves at each door opening would have the hardware removed and be fixed and would have the ability to be opened only when needed and not be allowed for egress.  Would provide total egress capacity of 244 occupants per door opening.  Consigli estimated this solution would cost approximately$566.00.

 

Option D  Install a bi-directional door which would provide directional traffic paths.  Egress width would be 3’-0”.  The egress capacity would be 244 occupants per door.  Total auditorium capacity is 382 occupants.  Consigli estimated this solution would cost approximately $8,853.00.

 

Dr. Dunham, Principal O’Rourke and Tim Farmer prefer Option B.

 

MOTION:  To adopt Option B not to exceed $22,038.00 with design changes to be made subsequently.  (Gladstone/Slater) unanimous

 

3.         Sharon Middle School Project

 

Reports

The following reports were received and are attached as part of these minutes:

 

Kaestle Boos:

 

David Morais conveyed to the Committee the following:  “Congratulations to the Sharon Middle School for achieving enough MA-CHPS points to receive provision MA-CHPS verified status. In addition, the Sharon Middle School project is the first project in the Commonwealth of Massachusetts to achieve this status on its first submission.”

 

He also mentioned that the new addition is more than 98% enclosed and the interior partition and mechanical, plumbing, fire protection and electrical rough-in is well underway.

The FF&E update report is attached to these minutes.

 

Samples of the building dedication plaque was passed around for the Standing Building Committee review.  Consigli issued a credit change order of ($3,131.00) for changing the building dedication plaque to cast aluminum in lieu of the specified brass.

 

MOTION:  to approve the building dedication plaque to cast aluminum with natural aluminum finish.  (Rice/Smith) unanimous

 

Consigli:

 

Michael Dupuis presented the attached Construction Manager’s Report.

 

Daedalus:

 

Bob White presented the attached OPM Report noting that there will be a Change Order Sub-Committee Meeting on Wednesday, February 16, 2011 at 7:00 a.m. at the Consigli construction trailer.

 

Sharon Middle School Phone System Approval

 

MOTION:  to approve the purchase of the Sharon Middle School phone system (Partners Communication, Inc.) at a purchase price of $68,947 (Benjamin/Croteau) unanimous

 

            MOTION:  To adjourn the meeting at 8:30 p.m.  (Benjamin/Smith) unanimous

 

Submitted:

 

Linda V. Morse, Secretary

Sharon Standing Building Committee

 

 

__________________________________                            ___________________

Signature of Chair                                                                   Date of Acceptance