Sharon Standing Building Committee
Meeting Minutes
March 29, 2011
Members Present: Chair Gordon Gladstone, Vice-Chair Deb Benjamin, Bill Croteau, Rick Rice, Fred Clay, Joel Wolk, Steve Smith, Roger Thibault and Glenn Allen
Members Not Present: Rich Slater and Colleen Tuck
Others Present: Joe Sullivan - Daedalus Projects Inc.
Michael Dupuis - Consigli Construction Co.
David Morais - KBA
Daniel Bass – Baker-Wohl Architects
Ken Wertz - School
The meeting of the Sharon Standing Building Committee was called to order at 6:30 p.m. at the Community Center Conference Room
1. Administration
Approval of Minutes
MOTION: To approve the meeting Sharon Standing Building Committee Regular Session
minutes of March 22, 2011 ( Slater/Tuck) unanimous - Joel Wolk, Deb Benjamin,
Steve Smith and Roger Thibault abstained as they were not at the meeting.
Future Meetings: April 12 and 26, 2011
2. Sharon Middle School Project Updates
The following reports were received and are attached as part of these minutes:
KBA – David Morais
Consigli – Michael Dupuis
· Floor 2 of the Middle School to be completed end of June;
· Floor 1 including new addition to be completed end of July
· Added seating in another section of the gym;
· After June 23, 2011 ready to start moving of classrooms to the second floor, furniture, etc.
Daedalus – Joe Sullivan
· April – changing of entrance to Middle School to be relocation – using new building entrance;
· Chair Gladstone received an email from MSBA re ribbon cutting. Possible ribbon cutting in May or June of 2012.
Approval of Change Order #4
Member Joel Wolk informed the SSBC that the Change Order Sub-Committee met on March 23, 2011 and found the requests for inclusion into Change Order #4 to be reasonable.
MOTION: To authorize the Chair or Vice Chair to execute Change Order #4 in the amount of $72,970 contingent on final review by DPI and KBA and signed acceptance by Consigli Construction. (Wolk/Clay) – unanimous
Approval of CM Contingency #2
Member Joel Wolk informed the SSBC that the Change Order Sub-Committee at their meeting on March 23, 2011, reviewed the items listed on CM contingency #2 and determined that they all met the CM Construction Agreement criteria for payment.
MOTION: To approve CM Contingency #2 items in the amount of $32,284. (Wolk/Smith) – unanimous
3. High School Roof
Daniel Bass – Baker-Wohl Architects - gave the following update on the project for the Sharon High School Green Roof Repair (Reports are attached)
· 60% CD Estimate submission summary;
· $3,764,669 base bid/$354,684 Add Alternate;
· Filed Sub Bids due April 21, 2011 – 2:00 p.m. (to be sent to the attention of Linda Morse, Secretary, Standing Building Committee, 90 South Main Street, Sharon, MA 02068;
· Standing Building Committee to meet either April 26 or 28, 2011. Date to be determined;
· Roof Contractor should be DCAM certified;
· Project Budget from DPI – internal cost estimate 30%;
· Richard Marks of DPI to review Budget
Chair Gladstone prepared spreadsheet as originally presented to Capital Outlay and DPI recommended. (attached)
· Capital outlay proposed contribution $2,438,000
· MSBA possible reimbursement 46.79%;
· Add warranty to the H.S. roof and not take alternate now;
· Town Meeting to vote on $4,601,414;
· Contingency – non reimbursable;
· The SSBC is comfortable with Chair Gladstone’s High School Roof spreadsheet.
Next Meeting: April 12, 2011 – Community Center Conference Room at 6:30 p.m.
MOTION: To adjourn the meeting at 8:00 p.m. (Wolk/Smith) - unanimous
Submitted:
Linda V. Morse, Secretary
Sharon Standing Building Committee
__________________________________ ___________________
Signature of Chair Date of Acceptance